Engineering Precision at 154 Metres

The installation of a structure of this scale at 154 metres above ground level required exceptional accuracy and planning. Every component needed to fit perfectly; any deviation would have created significant challenges once the crown reached its final position.

To ensure a seamless erection sequence, Bourne Steel carried out a full trial assembly at our South West facilities. This process:

  • Recreated the exact rooftop footprint of the tower
  • Simulated the restricted working environment at height
  • Allowed all interfaces, tolerances and geometry to be verified and refined
  • De‑risked the installation by resolving issues before components reached site

This ground‑level replication was essential in ensuring the crown could be installed safely, efficiently and without interruption.

Trial Assembly, Transport & Final Installation

Following successful trial erection:

  • The crown structure and working trestles were dismantled
  • All components were transported to London
  • Bourne Steel completed the final installation and erection atop the tower

The result is a visually striking and structurally critical feature that defines Highpoint’s skyline presence.